Contract 1: Heavy Civil and Airfield Lighting Approximately 80% of the contract work is complete with only 55.8% of the contract time used. Underground utilities are being installed in the …
The terminal at the new Panama City Airport located in West Bay in Bay County is moving along at a swift pace. The percentage complete is just under 20% with …
New aerials have been released of the construction progress at the new aiport site in West Bay in North Bay County. The new airport in Panama City Beach is located …
That’s right, the approved 8,400 feet of the main runway at the new airport site in Panama City is complete. With the exception of the center where the runway lights …
No talk, all pictures: This is looking from the south towards the north. The segment off to the right will be the cross-wind runway. To the far left of the …
Nearly a whopping 3 months ahead of schedule, the 10,000 foot primary runway is only weeks from seeing the first warm morsels of pavement. Although the current contract is for …
The construction of the new airport is on schedule with paving of the runway to begin in 12 weeks. With over 40 million cubic yards of material moved since the …
The construction of the new Panama City – Bay County International Airport is ahead of schedule. The entire 1300 acres of the initial footprint is cleared with crews to start …
Coastal Vision 3000 takes off with Milestone Presentation at Panama City – Bay County International Airport Site PANAMA CITY – Nearly 100 Northwest Florida business and community leaders came together …
Huge progress has been made since construction began at the beginning of the year at the new Panama City Bay County International Airport site north of up Highway 79 north …