Airport Updates

The New King of South Has Been Crowned

September 24, 2009 • 16 comments

l Early Tuesday morning, a milestone was reached at the New Panama City Beach – Bay County International Airport Site. The capping of the control, a significant accomplishment in airport …

by Cebo Campbell

15 Things to Know About the Development of the Old Airport Site

June 27, 2009 • 3 comments

Leucadia National Corporation/CAR/SABLC: Leucadia National Corporation is the parent company of Community Airport Redevelopment, which was changed to the St. Andrew Bay Land Company.  Leucadia has home offices in Salt …

by Jason Koertge

PC Airport Construction Update – PHOTOS

June 22, 2009 • 13 comments

The new Panama City Airport is less than 12 months from completion and the on site action is really accelerating.  With new construction milestones being made on a weekly basis, …

by Jason Koertge

Video of Environmental Damage at New Airport Site

May 28, 2009 • 6 comments

Having been up there, I was able to take video of the creeks and waterways that serve as the natural water run-off point for the new Panama City Airport.  Again, …

by Jason Koertge

Despite Reports, New Airport has Little Environmental Damage

May 25, 2009 • 20 comments

Despite other reports in the media, the construction of the new Panama City airport in West Bay has caused little disturbance in the natural environmental habitat of the pristine areas …

by Jason Koertge

How It’s Done – Paving a Runway Video

April 3, 2009 • 5 comments

So, I thought it would be cool to shoot a video on  how they paved the runway, and turns out, I was right – it is cool.  Maybe I’m a …

by Jason Koertge

New Airport Aerial Pictures and Update

March 18, 2009 • 1 comment

Contract 1: Heavy Civil and Airfield Lighting Approximately 80% of the contract work is complete with only 55.8% of the contract time used. Underground utilities are being installed in the …

by Jason Koertge

Airport Update – Pictures of the Terminal Progress

March 9, 2009 • 3 comments

The terminal at the new Panama City Airport located in West Bay in Bay County is moving along at a swift pace.  The percentage complete is just under 20% with …

by Jason Koertge

Airport Construction Update – Terminal 18% Complete

March 2, 2009 • 0 comments

Contract 1: Heavy Civil and Airfield Lighting Approximately 80% of the contract work is complete with only 54% of the contract time used. 90% of the 15” concrete paving lanes …

by Jason Koertge

New Aerials of the New Panama City Bay County International Airport

February 16, 2009 • 0 comments

New aerials have been released of the construction progress at the new aiport site in West Bay in North Bay County.  The new airport in Panama City Beach is located …

by Jason Koertge