Is the New PCB Airport Still on Schedule?

by August 31, 2009 • 1 comment

Panama City-Bay County International Airport is still on time to meet its completion date. Taken from a recent article on the NEW-PFN website, here is an updated rundown of construction on the new site.

Contract 1: Heavy Civil and Airfield Lighting
Approximately 91% of contract is complete with 80% of contract time used.

Pond C grading is 99% complete.
Installing Airfield Edge Lighting Conduit and Plazas
Continuing installation of Airside underdrain pipe
Terminal Apron concrete pad is complete
Morrell and Kelly Branch restoration continues

Contract 2: Terminal Building, ATCT and Support Buildings
Approximately 47% of contract is complete with 52% of contract time used.

Terminal:

In the utility area completed form work and compaction and preparing for concrete pour.
Continuing metal framing on 1st and 2nd levels.
In the baggage handling area continuing exterior CMU walls. Work is 60% complete.

Air Traffic Control Tower:

Preparing for concrete pour of stairs and deck Levels 2,3 and 4.
Installing decking and metal stairs floors 5-9.

Terminal Support Facilities:

Air Maintenance Facility – continuing electrical rough-in walls at maintenance office and bays.
Air Cargo Facility – continuing with the installation of MR gypsum wall board.

Rental Car Facility:

Beginning the erection of the pre-engineered metal building.

Public Safety Building:

Continuing block installation at 2nd level administration area.

Manpower:

An average of 155 personnel are on site Monday through Friday and approximately three workers are on site on Saturday.

Contract 3: Utility Contract
Approximately 57% of contract work is complete with 54% of contract time used.

3W2? Power Distribution Duct Bank is 95% complete; installation of wiring by Gulf Power is ongoing.
Street Light Duct Work is 98% complete; light poles being installed (approx. 6-8 per day).
6W4? Power Distribution Duct Bank is 100% complete.
Jack and boring on Main Access Road for fire hydrant installation.
24? Water Main is 98% complete.
12? water main is 99% complete.
30? water main is 90% complete; installation continuing on the utility road.

Lift Station:

Lift Station is 50% complete; plumbing is being installed.

Fuel Farm:

Fuel Farm is 25% complete; electrical work is in progress.

Booster Station:

Booster Station is 40% complete; concrete roofs are poured.

Triturator:

Triturator is 10% complete; vault installation is underway.

Contract 4: Landscape/Hardscape Contract
Approximately 7% of the work is complete with 11% of the contract time used.

Construction is underway on overflow weirs on Main Access Road
Performing soil preparation on Main Access Road.
Hydro seeding of Main Access Road is underway.
Installing aquatic plants at main entrance.

Print Story

Related Stories

Additional Airport Stories

More Ways to Connect with Us

Leave a Comment

{

1 Comment

}

1 Don September 1, 2009 at 9:00 am

Interesting note. I called about booking travel for next summer and Delta says they are still flying into old airport next June. They have no info about new airport.

Reply